How long does flat renovation take — realistic timelines by type of work

Brzix team · published 2026-08-26

One of the most common questions at the start of any renovation is: how long will this actually take? The honest answer depends on the type and scope of works. Here are realistic timelines — not the optimistic promises you hear at the start, but numbers based on how things typically go.

Minor works — timelines

Medium projects — timelines

Tip: always ask the tradesperson how many people will be on site. One tiler lays 10–15 m² per day; two will halve the time. The number of workers directly affects the timeline.

Full reconstruction — timelines

The biggest time-consumers in a full reconstruction are not the visible works — they are the drying and curing times. Screed takes 3–4 weeks to dry. Skim coat needs 2–3 weeks per layer. Waterproofing must cure before anything is laid on top. These waits cannot be skipped without compromising quality.

What slows down works

Warning: if someone tells you a complete renovation of a 60 m² flat will take 2–3 weeks — ask how many workers will be on site simultaneously. Without a large team working in parallel, that timeline is physically impossible when you factor in drying times.

How to plan without stress

  1. Add 30% to whatever the tradesperson estimates. This is not pessimism — it's how most renovations actually go.
  2. Order all materials before works begin. Don't let the renovation wait for a delivery.
  3. Make all decisions about materials and finishes in advance. Choosing tiles mid-renovation causes delays.
  4. Build in a buffer before any hard deadline (moving in, renting out, a visit from family). If you need to be in by 1 September, aim to finish by 15 August.