Flat renovation — the correct order of works

Brzix team · published 2026-08-26

The wrong order of works during renovation can literally cost you double. If you lay parquet and then call an electrician to run cables under the floor, the parquet gets lifted. If you paint before the screed is dry, the paint cracks. Here is the correct sequence, step by step.

Phase 1: demolition and preparation

Everything that comes down or out — goes first. This includes:

Demolition is dirty and noisy — schedule it at the start, while neighbours are still relatively patient.

Phase 2: rough construction works

After demolition, before everything else:

Phase 3: installations — electrics and plumbing

This is the critical phase that many people push too late. Installations go before the final wall and floor coverings, because pipes and cables must be inside the walls or floor.

Warning: do not pour the screed until the installations have been inspected and pressure-tested. Once the screed is poured there is no repair without breaking it up.

Phase 4: screed and floor levelling

Only after the installations, the floor is levelled with screed. The screed must dry for a minimum of 3–4 weeks before tiles or parquet are laid on it. Rushing this is one of the most common causes of floor problems.

Phase 5: tiles and floor coverings

Once the screed is dry and installations are complete:

Tip: lay floor tiles before wall tiles, because the wall tiles need to "sit" on the already-laid floor tiles — not directly on the screed.

Phase 6: plastering and skim-coating walls

After tiling, walls are finely plastered and skim-coated. The skim coat needs to dry seriously — depending on thickness and humidity, it can take 2–3 weeks per layer.

Phase 7: parquet or laminate

Parquet goes down only when all wet works are complete and dry. Moisture is parquet's number one enemy — if you lay it too early it will shrink or swell.

Phase 8: fitting joinery and sanitary ware

Phase 9: finishing works — painting

Painting goes at the very end, when all other works are finished. Painting before the parquet or sanitary ware means painting again afterwards.

Phase 10: clean-up and details